Bid Addendum Preflight Report — Kitsap County IFB 2026-016 (WA) — LS-to-TON Unit Trap & PDF Audit

Authoritative Latest Schedule: owner_05_bid_schedule_v2.xlsx · Contractor File: contractor_v2_unit_trap.xlsx · Full Deterministic Audit
Sample Data Notice: Built from the official public solicitation files with simulated contractor unit rates and controlled benchmark faults injected for verification.
Hard Blockers
2
Warnings
41
Quantified Risk
$6,940,875.00
Rows Audited
32
Safe Cells Written
28

Findings & Hard-Gate Checks

WARNING SPEC_CHANGED_REVIEW BID-SCHEDULE!G6

Item #1 specification changed vs prior schedule

Changed from 'MOBILIZATION (10% CONSTRUCTION COST)' to 'MOBILIZATION (10% CONSTRUCTION COST)'; confirm repricing.

Action: Verify unit price reflects the updated specification.

WARNING SPEC_CHANGED_REVIEW BID-SCHEDULE!G7

Item #2 specification changed vs prior schedule

Changed from 'CONSTRUCTION SURVEYING AND STAKING' to 'CONSTRUCTION SURVEYING AND STAKING'; confirm repricing.

Action: Verify unit price reflects the updated specification.

WARNING SPEC_CHANGED_REVIEW BID-SCHEDULE!G8

Item #3 specification changed vs prior schedule

Changed from 'CONSTRUCTION ACCESS, STAGING AND STOCKPILING AREAS' to 'CONSTRUCTION ACCESS, STAGING AND STOCKPILING AREAS'; confirm repricing.

Action: Verify unit price reflects the updated specification.

WARNING SPEC_CHANGED_REVIEW BID-SCHEDULE!G9

Item #4 specification changed vs prior schedule

Changed from 'EROSION CONTROL AND WATER POLLUTION PREVENTION' to 'EROSION CONTROL AND WATER POLLUTION PREVENTION'; confirm repricing.

Action: Verify unit price reflects the updated specification.

WARNING SPEC_CHANGED_REVIEW BID-SCHEDULE!G10

Item #5 specification changed vs prior schedule

Changed from ''GAZEEBO RELOCATION (1#)' to ''GAZEEBO RELOCATION (1#)'; confirm repricing.

Action: Verify unit price reflects the updated specification.

INFO BLANK_DELETED_ROW BID-SCHEDULE!R11

Item #6 is blank/deleted in latest schedule

Row 11 retains item number #6 with empty description/quantity.

Action: Leave blank; do not enter a price.

WARNING SPEC_CHANGED_REVIEW BID-SCHEDULE!G12

Item #7 specification changed vs prior schedule

Changed from ''TREE/PLANT PROTECTION' to ''TREE/PLANT PROTECTION'; confirm repricing.

Action: Verify unit price reflects the updated specification.

INFO BLANK_DELETED_ROW BID-SCHEDULE!R13

Item #8 is blank/deleted in latest schedule

Row 13 retains item number #8 with empty description/quantity.

Action: Leave blank; do not enter a price.

WARNING SPEC_CHANGED_REVIEW BID-SCHEDULE!G14

Item #9 specification changed vs prior schedule

Changed from 'CLEARING AND GRUBBING, INCLUDING PLANTING AREAS (~40,000SF)' to 'CLEARING AND GRUBBING, INCLUDING PLANTING AREAS (~40,000SF)'; confirm repricing.

Action: Verify unit price reflects the updated specification.

WARNING SPEC_CHANGED_REVIEW BID-SCHEDULE!G15

Item #10 specification changed vs prior schedule

Changed from 'SITE RESTORATION AND FINAL INSPECTION' to 'SITE RESTORATION AND FINAL INSPECTION'; confirm repricing.

Action: Verify unit price reflects the updated specification.

WARNING SPEC_CHANGED_REVIEW BID-SCHEDULE!G17

Item #11 specification changed vs prior schedule

Changed from 'DETERIORATED PILE REMOVAL, HAUL, DISPOSAL' to 'DETERIORATED PILE REMOVAL, HAUL, DISPOSAL'; confirm repricing.

Action: Verify unit price reflects the updated specification.

WARNING DESC_UNIT_CONFLICT BID-SCHEDULE!G18

Item #12A description mentions CY while pricing unit is LS

Row 18 description states 'EST. 50CY', but official billing unit is LS (Qty 1).

Action: Confirm your unit price is per LS, not per CY.

WARNING SPEC_CHANGED_REVIEW BID-SCHEDULE!G18

Item #12A specification changed vs prior schedule

Changed from 'ROCK ARMOR REMOVAL, SALVAGING FOR REUSE (EST. 50CY ROCK, 25C' to 'ROCK ARMOR REMOVAL, SALVAGING FOR REUSE ONSITE (EST. 50CY RO'; confirm repricing.

Action: Verify unit price reflects the updated specification.

WARNING SPEC_CHANGED_REVIEW BID-SCHEDULE!G19

Item #12B specification changed vs prior schedule

Changed from 'ROCK ARMOR REMOVAL, SALVAGING AND STOCKPILING LOCALLY (EST. ' to 'ROCK ARMOR REMOVAL, SALVAGING AND STOCKPILING LOCALLY (EST. '; confirm repricing.

Action: Verify unit price reflects the updated specification.

BLOCKER UNIT_CHANGED_BLOCKED BID-SCHEDULE!G20 Risk: $3,375.00

Item #12C pricing unit changed (CY → TON)

BID-SCHEDULE!G20 'ROCK ARMOR REMOVAL (NONUSABLE, EST. 50CY), HAUL, DISPOS' changed from 190 CY to 75 TON.

Action: Re-price strictly per TON; never reuse prior CY rate.

WARNING DESC_UNIT_CONFLICT BID-SCHEDULE!G20

Item #12C description mentions CY while pricing unit is TON

Row 20 description states 'EST. 50CY', but official billing unit is TON (Qty 75).

Action: Confirm your unit price is per TON, not per CY.

WARNING SPEC_CHANGED_REVIEW BID-SCHEDULE!G21

Item #12D specification changed vs prior schedule

Changed from 'TWO ROCK SILL REFORMATION' to 'TWO ROCK SILL REFORMATION'; confirm repricing.

Action: Verify unit price reflects the updated specification.

BLOCKER UNIT_CHANGED_BLOCKED BID-SCHEDULE!G22 Risk: $6,937,500.00

Item #13 pricing unit changed (LS → TON)

BID-SCHEDULE!G22 'CONC. RUBBLE, SPALLS, WOOD WALL & DEBRIS REMOVAL, HAUL,' changed from 1 LS to 375 TON. CRITICAL: Contractor entered 18,500.00 per TON × 375 = 6,937,500.00, consistent with copying an old Lump Sum price into a unit-rate column!

Action: Re-price strictly per TON; never reuse prior LS rate.

WARNING DESC_UNIT_CONFLICT BID-SCHEDULE!G22

Item #13 description mentions CY while pricing unit is TON

Row 22 description states 'EST. TOTAL 268 CY', but official billing unit is TON (Qty 375).

Action: Confirm your unit price is per TON, not per CY.

WARNING DESC_UNIT_CONFLICT BID-SCHEDULE!G24

Item #14 description mentions CY while pricing unit is LS

Row 24 description states 'EST. TOTAL 1200 CY', but official billing unit is LS (Qty 1).

Action: Confirm your unit price is per LS, not per CY.

WARNING SPEC_CHANGED_REVIEW BID-SCHEDULE!G24

Item #14 specification changed vs prior schedule

Changed from 'BANK / INLAND EXCAVATION & GRADING, INCL OVER EX., HAUL (EST' to 'BANK / INLAND EXCAVATION & GRADING, INCL OVER EX., HAUL (EST'; confirm repricing.

Action: Verify unit price reflects the updated specification.

WARNING SPEC_CHANGED_REVIEW BID-SCHEDULE!G25

Item #15 specification changed vs prior schedule

Changed from ''STORMWATER OUTFALL PIPE SAWCUT AND STABILIZATION' to ''STORMWATER OUTFALL PIPE SAWCUT AND STABILIZATION'; confirm repricing.

Action: Verify unit price reflects the updated specification.

WARNING SPEC_CHANGED_REVIEW BID-SCHEDULE!G26

Item #16 specification changed vs prior schedule

Changed from 'OUTFALL PIPE RECONNECTION (OPTIONAL, FIELD VERIFY)' to 'OUTFALL PIPE RECONNECTION (OPTIONAL, FIELD VERIFY)'; confirm repricing.

Action: Verify unit price reflects the updated specification.

WARNING SPEC_CHANGED_REVIEW BID-SCHEDULE!G28

Item #17 specification changed vs prior schedule

Changed from 'PIT-RUN GRAVEL-SAND PLACEMENT' to 'PIT-RUN GRAVEL-SAND PLACEMENT'; confirm repricing.

Action: Verify unit price reflects the updated specification.

WARNING SPEC_CHANGED_REVIEW BID-SCHEDULE!G29

Item #18 specification changed vs prior schedule

Changed from 'COARSE SAND MIXED WITH PIT-RUN GRAVEL-SAND (INCL. MIXING)' to 'COARSE SAND MIXED WITH PIT-RUN GRAVEL-SAND (INCL. MIXING)'; confirm repricing.

Action: Verify unit price reflects the updated specification.

WARNING SPEC_CHANGED_REVIEW BID-SCHEDULE!G30

Item #19 specification changed vs prior schedule

Changed from 'COBBLE TOE (MIX IMPORTED COBBLE WITH 20% NATIVE SEDIMENT)' to 'COBBLE TOE (MIX IMPORTED COBBLE WITH 20% NATIVE SEDIMENT)'; confirm repricing.

Action: Verify unit price reflects the updated specification.

WARNING DESC_UNIT_CONFLICT BID-SCHEDULE!G32

Item #20 description mentions CY while pricing unit is LS

Row 32 description states 'EST. 56 CY', but official billing unit is LS (Qty 1).

Action: Confirm your unit price is per LS, not per CY.

WARNING SPEC_CHANGED_REVIEW BID-SCHEDULE!G32

Item #20 specification changed vs prior schedule

Changed from 'MOSTLY BURIED RETAINING WALL, SALVAGED ROCK & SPALLS (EST. 5' to 'MOSTLY BURIED RETAINING WALL, SALVAGED ROCK & SPALLS (EST. 5'; confirm repricing.

Action: Verify unit price reflects the updated specification.

WARNING DESC_UNIT_CONFLICT BID-SCHEDULE!G33

Item #21 description mentions CY while pricing unit is LS

Row 33 description states 'EST. 19 CY', but official billing unit is LS (Qty 1).

Action: Confirm your unit price is per LS, not per CY.

WARNING SPEC_CHANGED_REVIEW BID-SCHEDULE!G33

Item #21 specification changed vs prior schedule

Changed from 'RETURN WALL & SPOT REPAIR, SALVAGED ROCK & SPALLS (EST. 19 C' to 'RETURN WALL & SPOT REPAIR, SALVAGED ROCK & SPALLS (EST. 19 C'; confirm repricing.

Action: Verify unit price reflects the updated specification.

WARNING SPEC_CHANGED_REVIEW BID-SCHEDULE!G35

Item #22 specification changed vs prior schedule

Changed from 'PIT-RUN GRAVEL-SAND MIX (OR USE/MIX WITH NATIVE SEDIMENT - F' to 'PIT-RUN GRAVEL-SAND MIX (OR USE/MIX WITH NATIVE SEDIMENT - F'; confirm repricing.

Action: Verify unit price reflects the updated specification.

WARNING SPEC_CHANGED_REVIEW BID-SCHEDULE!G36

Item #23 specification changed vs prior schedule

Changed from 'COARSE SAND (60%) MIXED WITH PIT-RUN GRAVEL-SAND (40%)' to 'COARSE SAND (60%) MIXED WITH PIT-RUN GRAVEL-SAND (40%)'; confirm repricing.

Action: Verify unit price reflects the updated specification.

WARNING SPEC_CHANGED_REVIEW BID-SCHEDULE!G37

Item #24 specification changed vs prior schedule

Changed from ''1.5"-4" SIZE STREAMBED COBBLE' to ''1.5"-4" SIZE STREAMBED COBBLE'; confirm repricing.

Action: Verify unit price reflects the updated specification.

WARNING SPEC_CHANGED_REVIEW BID-SCHEDULE!G38

Item #25 specification changed vs prior schedule

Changed from 'GEOTEXTILE, MIRAFI™ 1100N or EQUIVALENT (FOR WALLS)' to 'GEOTEXTILE, MIRAFI™ 1100N or EQUIVALENT (FOR WALLS)'; confirm repricing.

Action: Verify unit price reflects the updated specification.

WARNING SPEC_CHANGED_REVIEW BID-SCHEDULE!G39

Item #26 specification changed vs prior schedule

Changed from 'WOOD CHIP MULCH (MATERIAL ONLY, IMPORT AND STOCKPILE ONSITE)' to 'WOOD CHIP MULCH (MATERIAL ONLY, IMPORT AND STOCKPILE ONSITE)'; confirm repricing.

Action: Verify unit price reflects the updated specification.

WARNING SPEC_CHANGED_REVIEW BID-SCHEDULE!G41

Item #27 specification changed vs prior schedule

Changed from 'MULCH COVERED PEDESTRIAN PATHS (669 SF, 4" DEPTH) USING SALV' to 'MULCH COVERED PEDESTRIAN PATHS (669 SF, 4" DEPTH) USING SALV'; confirm repricing.

Action: Verify unit price reflects the updated specification.

WARNING SPEC_CHANGED_REVIEW BID-SCHEDULE!G42

Item #28 specification changed vs prior schedule

Changed from 'SOIL AMENDMENT & PLANTING BED PREPARATION (RIP COMPOST & TIL' to 'SOIL AMENDMENT & PLANTING BED PREPARATION (RIP COMPOST & TIL'; confirm repricing.

Action: Verify unit price reflects the updated specification.

WARNING SPEC_CHANGED_REVIEW BID-SCHEDULE!G43

Item #29 specification changed vs prior schedule

Changed from 'HABITAT LOGS (INCLUDING PLACEMENT), OPTIONAL' to 'HABITAT LOGS (INCLUDING PLACEMENT), OPTIONAL'; confirm repricing.

Action: Verify unit price reflects the updated specification.

INFO ITEM_DELETED_IN_ADDENDUM PDF:p1!R14

Prior item #6 (WATER SPIGOT RELOCATION (1#)) removed in latest schedule

Removed from Base Bid (previously 1 LS). Ensure prior cost is excluded from totals.

Action: Confirm removal and verify supplier quotes/subtotals exclude this item.

INFO ITEM_DELETED_IN_ADDENDUM PDF:p1!R18

Prior item #8 (REDWOOD TREE TRANSPLANT) removed in latest schedule

Removed from Base Bid (previously 1 LS). Ensure prior cost is excluded from totals.

Action: Confirm removal and verify supplier quotes/subtotals exclude this item.

WARNING NO_SUBTOTAL_FORMULAS contractor_v2_unit_trap.xlsx

Schedule has no Excel formulas on subtotal/total rows

All subtotal/total cells are static values or blank; verify manual arithmetic against independent Decimal totals.

Action: Cross-check every manually entered subtotal against the Audit Totals table.

WARNING EXTERNAL_WORKBOOK_LINKS BID-SCHEDULE!C16

Workbook package contains 10 external file link(s)

External references detected at BID-SCHEDULE!C16, BID-SCHEDULE!C23, BID-SCHEDULE!C27, BID-SCHEDULE!C31, BID-SCHEDULE!C34, BID-SCHEDULE!C16, BID-SCHEDULE!C23, BID-SCHEDULE!C27 (e.g. `='[1]Cost Detail'!D30`). Never rely on external links for pricing calculations.

Action: Do not refresh broken external links; replace any pricing external links with explicit numeric rates.

WARNING PDF_HIDDEN_DELIVERABLE owner_02_addendum_1.pdf:p.1

Required deliverable / compliance item: Pollution Liability

Found in owner_02_addendum_1.pdf p.1: "the bid opening and Due date May 15, 2026, at 2:00 PM. Adds contract requirement: INSURANCE: Environmental Pollution Liability and Remediation: Contractor shall provide Environmental Pollution Liability and/or Errors and"

Action: Include this required document/statement with final bid submission.

WARNING ADDENDUM_DATE_CONFLICT owner_02_addendum_1.pdf:p.1

Addendum date/weekday mismatch: claims Wednesday for 2026-05-15 (actually Friday)

owner_02_addendum_1.pdf p.1: "O: All Respondents FROM: Glen McNeill. Purchasing Supervisor CLOSING DATE: Wednesday 05/15/2026 @2:00 pm (CHANGED) REF NO.: 2026-016 IFB DYES INLET BULKHEAD REMOVAL AND SHORELINE"

Action: Verify official closing date/time with contracting agency.

WARNING ADDENDUM_DATE_CONFLICT owner_03_addendum_2.pdf:p.1

Addendum date/weekday mismatch: claims Wednesday for 2026-05-15 (actually Friday)

owner_03_addendum_2.pdf p.1: "All Respondents FROM: Glen McNeill. Purchasing Supervisor CLOSING DATE: Wednesday 05/15/2026 @2:00 pm (CHANGED) REF NO.: 2026-016 IFB DYES INLET BULKHEAD REMOVAL AND SHORELINE"

Action: Verify official closing date/time with contracting agency.

WARNING PDF_HIDDEN_DELIVERABLE owner_03_addendum_2.pdf:p.2

Required deliverable / compliance item: work window

Found in owner_03_addendum_2.pdf p.2: "bid Item 6, “WATER SPIGOT RELOCATION”, is now removed in the updated Bid Schedule. 7. Clarify work windows during tidal cycles. • Any work done below the OHWM must be done at low tide when dry, or, for"

Action: Include this required document/statement with final bid submission.

WARNING ADDENDUM_DATE_CONFLICT owner_04_addendum_3.pdf:p.1

Addendum date/weekday mismatch: claims Wednesday for 2026-05-15 (actually Friday)

owner_04_addendum_3.pdf p.1: "All Respondents FROM: Glen McNeill. Purchasing Supervisor CLOSING DATE: Wednesday 05/15/2026 @2:00 pm (CHANGED) REF NO.: 2026-016 IFB DYES INLET BULKHEAD REMOVAL AND SHORELINE"

Action: Verify official closing date/time with contracting agency.

Independent Decimal Group Totals

SheetGroupActive ItemsPricedIndependent TotalReported TotalStatus
BID-SCHEDULE Base Bid 30 30 / 30 $7,261,365.00 $7,261,365.00 OK

Complete Line-by-Line Audit (32 total rows · 32 flagged / changed)

CellGroupItem#Description Latest Qty/UnitPrior Qty/Unit Contractor RateStatusAudit Note
BID-SCHEDULE!R6 Base Bid 1 MOBILIZATION (10% CONSTRUCTION COST) 1 LS 1 LS $12,000.00 EXACT_SAFE Specification changed vs prior schedule (confirm repricing).
BID-SCHEDULE!R7 Base Bid 2 CONSTRUCTION SURVEYING AND STAKING 1 LS 1 LS $12,000.00 EXACT_SAFE Specification changed vs prior schedule (confirm repricing).
BID-SCHEDULE!R8 Base Bid 3 CONSTRUCTION ACCESS, STAGING AND STOCKPILING AREAS 1 LS 1 LS $12,000.00 EXACT_SAFE Specification changed vs prior schedule (confirm repricing).
BID-SCHEDULE!R9 Base Bid 4 EROSION CONTROL AND WATER POLLUTION PREVENTION 1 LS 1 LS $12,000.00 EXACT_SAFE Specification changed vs prior schedule (confirm repricing).
BID-SCHEDULE!R10 Base Bid 5 'GAZEEBO RELOCATION (1#) 1 LS 1 LS $12,000.00 EXACT_SAFE Specification changed vs prior schedule (confirm repricing).
BID-SCHEDULE!R11 Base Bid 6 (Blank / Deleted Row) — BLANK_DELETED_ROW Deleted blank row in latest owner schedule.
BID-SCHEDULE!R12 Base Bid 7 'TREE/PLANT PROTECTION 1 LS 1 LS $12,000.00 EXACT_SAFE Specification changed vs prior schedule (confirm repricing).
BID-SCHEDULE!R13 Base Bid 8 (Blank / Deleted Row) — BLANK_DELETED_ROW Deleted blank row in latest owner schedule.
BID-SCHEDULE!R14 Base Bid 9 CLEARING AND GRUBBING, INCLUDING PLANTING AREAS (~40,000SF) 1 LS 1 LS $12,000.00 EXACT_SAFE Specification changed vs prior schedule (confirm repricing).
BID-SCHEDULE!R15 Base Bid 10 SITE RESTORATION AND FINAL INSPECTION 1 LS 1 LS $12,000.00 EXACT_SAFE Specification changed vs prior schedule (confirm repricing).
BID-SCHEDULE!R17 Base Bid 11 DETERIORATED PILE REMOVAL, HAUL, DISPOSAL 14 EA 14 EA $85.00 EXACT_SAFE Specification changed vs prior schedule (confirm repricing).
BID-SCHEDULE!R18 Base Bid 12A ROCK ARMOR REMOVAL, SALVAGING FOR REUSE ONSITE (EST. 50CY ROCK, 25CY SPALLS, REUSE FOR WALLS) 1 LS 1 LS $12,000.00 EXACT_SAFE Specification changed vs prior schedule (confirm repricing).
BID-SCHEDULE!R19 Base Bid 12B ROCK ARMOR REMOVAL, SALVAGING AND STOCKPILING LOCALLY (EST. 130 CY, STOCKPILE SITE ~6 MILES AWAY) 200 CY 60 CY $85.00 EXACT_SAFE Specification changed vs prior schedule (confirm repricing).
BID-SCHEDULE!R20 Base Bid 12C ROCK ARMOR REMOVAL (NONUSABLE, EST. 50CY), HAUL, DISPOSAL 75 TON 190 CY $45.00 UNIT_CHANGED_BLOCKED BLOCKED: pricing unit changed CY -> TON.
BID-SCHEDULE!R21 Base Bid 12D TWO ROCK SILL REFORMATION 1 LS 1 LS $12,000.00 EXACT_SAFE Specification changed vs prior schedule (confirm repricing).
BID-SCHEDULE!R22 Base Bid 13 CONC. RUBBLE, SPALLS, WOOD WALL & DEBRIS REMOVAL, HAUL, DISPOSAL (EST. TOTAL 268 CY) 375 TON 1 LS $18,500.00 UNIT_CHANGED_BLOCKED BLOCKED: pricing unit changed LS -> TON.
BID-SCHEDULE!R24 Base Bid 14 BANK / INLAND EXCAVATION & GRADING, INCL OVER EX., HAUL (EST. TOTAL 1200 CY, SALVAGING QUANTITY TBD) 1 LS 1 LS $12,000.00 EXACT_SAFE Specification changed vs prior schedule (confirm repricing).
BID-SCHEDULE!R25 Base Bid 15 'STORMWATER OUTFALL PIPE SAWCUT AND STABILIZATION 4 EA 4 EA $85.00 EXACT_SAFE Specification changed vs prior schedule (confirm repricing).
BID-SCHEDULE!R26 Base Bid 16 OUTFALL PIPE RECONNECTION (OPTIONAL, FIELD VERIFY) 1 EA 1 EA $85.00 EXACT_SAFE Specification changed vs prior schedule (confirm repricing).
BID-SCHEDULE!R28 Base Bid 17 PIT-RUN GRAVEL-SAND PLACEMENT 150 CY 150 CY $85.00 EXACT_SAFE Specification changed vs prior schedule (confirm repricing).
BID-SCHEDULE!R29 Base Bid 18 COARSE SAND MIXED WITH PIT-RUN GRAVEL-SAND (INCL. MIXING) 80 CY 80 CY $85.00 EXACT_SAFE Specification changed vs prior schedule (confirm repricing).
BID-SCHEDULE!R30 Base Bid 19 COBBLE TOE (MIX IMPORTED COBBLE WITH 20% NATIVE SEDIMENT) 150 CY 150 CY $85.00 EXACT_SAFE Specification changed vs prior schedule (confirm repricing).
BID-SCHEDULE!R32 Base Bid 20 MOSTLY BURIED RETAINING WALL, SALVAGED ROCK & SPALLS (EST. 56 CY) 1 LS 1 LS $12,000.00 EXACT_SAFE Specification changed vs prior schedule (confirm repricing).
BID-SCHEDULE!R33 Base Bid 21 RETURN WALL & SPOT REPAIR, SALVAGED ROCK & SPALLS (EST. 19 CY) 1 LS 1 LS $12,000.00 EXACT_SAFE Specification changed vs prior schedule (confirm repricing).
BID-SCHEDULE!R35 Base Bid 22 PIT-RUN GRAVEL-SAND MIX (OR USE/MIX WITH NATIVE SEDIMENT - FIELD VERIFY) 225 TON 225 TON $85.00 EXACT_SAFE Specification changed vs prior schedule (confirm repricing).
BID-SCHEDULE!R36 Base Bid 23 COARSE SAND (60%) MIXED WITH PIT-RUN GRAVEL-SAND (40%) 120 TON 120 TON $85.00 EXACT_SAFE Specification changed vs prior schedule (confirm repricing).
BID-SCHEDULE!R37 Base Bid 24 '1.5"-4" SIZE STREAMBED COBBLE 200 TON 180 TON $85.00 EXACT_SAFE Specification changed vs prior schedule (confirm repricing).
BID-SCHEDULE!R38 Base Bid 25 GEOTEXTILE, MIRAFI™ 1100N or EQUIVALENT (FOR WALLS) 120 SY 120 SY $85.00 EXACT_SAFE Specification changed vs prior schedule (confirm repricing).
BID-SCHEDULE!R39 Base Bid 26 WOOD CHIP MULCH (MATERIAL ONLY, IMPORT AND STOCKPILE ONSITE) 256 CY 256 CY $85.00 EXACT_SAFE Specification changed vs prior schedule (confirm repricing).
BID-SCHEDULE!R41 Base Bid 27 MULCH COVERED PEDESTRIAN PATHS (669 SF, 4" DEPTH) USING SALVAGED MULCH FROM TESC FOR CONSTRUCTION ACCESS 1 LS 1 LS $12,000.00 EXACT_SAFE Specification changed vs prior schedule (confirm repricing).
BID-SCHEDULE!R42 Base Bid 28 SOIL AMENDMENT & PLANTING BED PREPARATION (RIP COMPOST & TILL) 270 CY 270 CY $85.00 EXACT_SAFE Specification changed vs prior schedule (confirm repricing).
BID-SCHEDULE!R43 Base Bid 29 HABITAT LOGS (INCLUDING PLACEMENT), OPTIONAL 4 EA 4 EA $85.00 EXACT_SAFE Specification changed vs prior schedule (confirm repricing).

Addendum PDF & Deliverable Evidence (7 signals)

PDF FilePageAdd.#LevelExtracted Requirement & Exact Source Quote
owner_02_addendum_1.pdf p.1 1 WARNING Required deliverable / compliance item: Pollution Liability
the bid opening and Due date May 15, 2026, at 2:00 PM. Adds contract requirement: INSURANCE: Environmental Pollution Liability and Remediation: Contractor shall provide Environmental Pollution Liability and/or Errors and
owner_02_addendum_1.pdf p.1 1 WARNING Addendum date/weekday mismatch: claims Wednesday for 2026-05-15 (actually Friday)
O: All Respondents FROM: Glen McNeill. Purchasing Supervisor CLOSING DATE: Wednesday 05/15/2026 @2:00 pm (CHANGED) REF NO.: 2026-016 IFB DYES INLET BULKHEAD REMOVAL AND SHORELINE
owner_03_addendum_2.pdf p.1 2 WARNING Addendum date/weekday mismatch: claims Wednesday for 2026-05-15 (actually Friday)
All Respondents FROM: Glen McNeill. Purchasing Supervisor CLOSING DATE: Wednesday 05/15/2026 @2:00 pm (CHANGED) REF NO.: 2026-016 IFB DYES INLET BULKHEAD REMOVAL AND SHORELINE
owner_03_addendum_2.pdf p.2 2 WARNING Unit / pricing basis change noted in addendum prose
ineer at PW rock shop as a verification. This work will be covered by revised Bid Item 12B paid for by unit price per CY. Rock material if disapproved for stockpiling by the PW or the Engineer will be treated as rubble o
owner_03_addendum_2.pdf p.2 2 WARNING Required deliverable / compliance item: work window
bid Item 6, “WATER SPIGOT RELOCATION”, is now removed in the updated Bid Schedule. 7. Clarify work windows during tidal cycles. • Any work done below the OHWM must be done at low tide when dry, or, for
owner_03_addendum_2.pdf p.3 2 WARNING Required deliverable / compliance item: work window
be consistent with this requirement). However, the contractor is asked to submit the planned/committed work window together with the bid schedule. END OF ADDENDUM NO. 2
owner_04_addendum_3.pdf p.1 3 WARNING Addendum date/weekday mismatch: claims Wednesday for 2026-05-15 (actually Friday)
All Respondents FROM: Glen McNeill. Purchasing Supervisor CLOSING DATE: Wednesday 05/15/2026 @2:00 pm (CHANGED) REF NO.: 2026-016 IFB DYES INLET BULKHEAD REMOVAL AND SHORELINE