Owner latest schedule marks 2026-06-19!Row 109 with strikethrough formatting (retaining quantity 5.25 l.m), but contractor entered rate=120, amount=630 (inflating total by 630.00).
Action: Remove rate, formulas, and extended amount from struck-through row and recalculate subtotal.
Row 110 was previously item #11 priced at 1500, but in revised schedule #10 contractor entered 650 (matching an adjacent item's prior rate after renumbering).
Action: Restore semantic item rate 1500 or confirm deliberate repricing.
Row 111 was previously item #12 priced at 650, but in revised schedule #11 contractor entered 1500 (matching an adjacent item's prior rate after renumbering).
Action: Restore semantic item rate 650 or confirm deliberate repricing.
Removed from Site 7 (previously 5.25 l.m). Ensure prior cost is excluded from totals.
Action: Confirm removal and verify supplier quotes/subtotals exclude this item.
Subtotal: 22791 reports 22,791.00, but independent sum of active lines is 22,161.00 (delta +630.00).
Action: Update 2026-06-19!F112 to 22,161.00.
All subtotal/total cells are static values or blank; verify manual arithmetic against independent Decimal totals.
Action: Cross-check every manually entered subtotal against the Audit Totals table.
Found in owner_02_addendum_01.pdf p.1: "D Item No. Questions 1. Question: Per RFQ section 4.2.1.5 is a Project Specific Safety Plan an acceptable alternative to COR certification requirements?"
Action: Include this required document/statement with final bid submission.
Found in owner_02_addendum_01.pdf p.1: "e Project Specific Safety Plan will be evaluated under Category 4 in lieu of COR/SECOR Certified. If successful, the proponent shall submit a Project Specific Saf"
Action: Include this required document/statement with final bid submission.
| Sheet | Group | Active Items | Priced | Independent Total | Reported Total | Status |
|---|---|---|---|---|---|---|
| 2026-06-19 | Site 1 | 13 | 13 / 13 | $21,616.00 | — | OK |
| 2026-06-19 | Site 2 | 7 | 7 / 7 | $6,035.40 | — | OK |
| 2026-06-19 | Site 3 | 12 | 12 / 12 | $31,248.00 | — | OK |
| 2026-06-19 | Site 4 | 6 | 6 / 6 | $13,728.20 | — | OK |
| 2026-06-19 | Site 5 | 14 | 14 / 14 | $270,396.20 | — | OK |
| 2026-06-19 | Site 6 | 13 | 13 / 13 | $28,283.90 | — | OK |
| 2026-06-19 | Site 7 | 11 | 11 / 11 | $22,161.00 | $22,791.00 | MISMATCH |
| Cell | Group | Item# | Description | Latest Qty/Unit | Prior Qty/Unit | Contractor Rate | Status | Audit Note |
|---|---|---|---|---|---|---|---|---|
| 2026-06-19!R4 | Site 1 | 1 | General Requirements | 1 LS | 1 LS | $54.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R5 | Site 1 | 2 | Traffic Control and Accomodation | 1 LS | 1 LS | $55.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R6 | Site 1 | 3 | Erosion and Sediment Control | 1 LS | 1 LS | $56.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R7 | Site 1 | 4 | Concrete Sidewalk Removal | 10 m2 | 10 m2 | $57.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R8 | Site 1 | 5 | Curb & Gutter Removal | 12 l.m | 12 l.m | $58.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R9 | Site 1 | 6 | Topsoil Stripping | 120 m2 | 120 m2 | $59.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R10 | Site 1 | 7 | Concrete Sidewalk Installation | 120 m2 | 120 m2 | $60.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R11 | Site 1 | 8 | Concrete Curb and Gutter | 76 l.m | 76 l.m | $61.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R12 | Site 1 | 9 | Concrete Pedestrian Ramp c/w Tactile Plates | 2 EA | 2 EA | $62.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R13 | Site 1 | 10 | Pedestrian Crossings | 12 l.m | 12 l.m | $63.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R14 | Site 1 | 11 | Pedestrian Crossing Signs c/w Base | 2 EA | 2 EA | $64.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R15 | Site 1 | 12 | Relocate Existing Signage | 3 EA | 3 EA | $65.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R16 | Site 1 | 13 | Shift Garbage Bins and Concrete Pad | 1 LS | 1 LS | $66.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R22 | Site 2 | 1 | General Requirements | 1 LS | 1 LS | $72.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R23 | Site 2 | 2 | Traffic Control and Accomodation | 1 LS | 1 LS | $73.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R24 | Site 2 | 3 | Erosion and Sediment Control | 1 LS | 1 LS | $74.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R25 | Site 2 | 4 | Topsoil Stripping | 33 m2 | 33 m2 | $75.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R26 | Site 2 | 5 | Concrete Sidewalk Installation | 10.4 m2 | 10.4 m2 | $76.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R27 | Site 2 | 6 | Concrete Bus Pad | 23 m2 | 23 m2 | $77.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R28 | Site 2 | 7 | Imported Fill | 10 m3 | 10 m3 | $78.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R34 | Site 3 | 1 | General Requirements | 1 LS | 1 LS | $84.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R35 | Site 3 | 2 | Traffic Control and Accomodation | 1 LS | 1 LS | $85.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R36 | Site 3 | 3 | Erosion and Sediment Control | 1 LS | 1 LS | $86.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R37 | Site 3 | 4 | Topsoil Stripping | 182 m2 | 182 m2 | $87.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R38 | Site 3 | 5 | Concrete Sidewalk Installation | 50 m2 | 50 m2 | $88.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R39 | Site 3 | 6 | Concrete Bus Pad | 60 m2 | 60 m2 | $89.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R40 | Site 3 | 7 | Concrete Curb and Gutter | 46 l.m | 46 l.m | $90.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R41 | Site 3 | 8 | Supply and Install Roam Bus Stop Signage | 1 EA | 1 EA | $91.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R42 | Site 3 | 9 | Supply and Install Signage | 2 EA | 2 EA | $92.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R43 | Site 3 | 10 | Relocate Existing Signage | 1 EA | 1 EA | $93.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R44 | Site 3 | 11 | Install Garbage Bin and Concrete Pad | 1 LS | 1 LS | $94.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R45 | Site 3 | 12 | Extend SD 450 CSP Culvert | 8.6 l.m | 8.6 l.m | $95.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R51 | Site 4 | 1 | General Requirements | 1 LS | 1 LS | $101.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R52 | Site 4 | 2 | Traffic Control and Accomodation | 1 LS | 1 LS | $102.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R53 | Site 4 | 3 | Erosion and Sediment Control | 1 LS | 1 LS | $103.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R54 | Site 4 | 4 | Remove and Dispose of Existing Asphalt | 72.3 m2 | 72.3 m2 | $104.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R55 | Site 4 | 5 | Concrete Sidewalk Installation | 33 m2 | 33 m2 | $105.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R56 | Site 4 | 6 | Concrete Curb and Gutter | 23 l.m | 23 l.m | $106.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R62 | Site 5 | 1 | General Requirements | 1 LS | 1 LS | $112.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R63 | Site 5 | 2 | Traffic Control and Accomodation | 1 LS | 1 LS | $113.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R64 | Site 5 | 3 | Erosion and Sediment Control | 1 LS | 1 LS | $114.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R65 | Site 5 | 4 | Concrete Sidewalk Removal | 9 m2 | 9 m2 | $115.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R66 | Site 5 | 5 | Curb & Gutter Removal | 10.2 l.m | 10.2 l.m | $116.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R67 | Site 5 | 6 | Full Depth Milling (50mm) of Existing Asphalt (PROVISIONAL) | 700 m2 | 700 m2 | $117.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R68 | Site 5 | 7 | Tack Coat (PROVISIONAL) | 600 m2 | 600 m2 | $118.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R69 | Site 5 | 8 | Asphalt Concrete Pavement Overlay - Calgary Type "B" Mix (PG 64-34), 50mm Compacted Thickness (PROVISIONAL) | 600 m2 | 600 m2 | $119.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R70 | Site 5 | 9 | Concrete Bus Bay (PROVISIONAL) | 184 m2 | 184 m2 | $120.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R71 | Site 5 | 10 | Concrete Bus Pad | 102 m2 | 102 m2 | $121.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R72 | Site 5 | 11 | Concrete Curb and Gutter | 60 l.m | 60 l.m | $122.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R73 | Site 5 | 12 | Concrete Pedestrian Ramp c/w Tactile Plates | 1 EA | 1 EA | $123.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R74 | Site 5 | 13 | Supply and Install Street Light Foundation and Rod | 1 EA | 1 EA | $124.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R75 | Site 5 | 14 | Supply and Install Street Light Conduit | 14 l.m | 14 l.m | $125.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R82 | Site 6 | 1 | General Requirements | 1 LS | 1 LS | $132.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R83 | Site 6 | 2 | Traffic Control and Accomodation | 1 LS | 1 LS | $133.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R84 | Site 6 | 3 | Erosion and Sediment Control | 1 LS | 1 LS | $134.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R85 | Site 6 | 4 | Remove and Dispose Existing Landscape Boulders | 1 LS | 1 LS | $135.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R86 | Site 6 | 5 | Concrete Sidewalk Removal | 9 m2 | 9 m2 | $136.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R87 | Site 6 | 6 | Curb & Gutter Removal | 5.7 l.m | 5.7 l.m | $137.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R88 | Site 6 | 7 | Concrete Sidewalk Installation | 162 m2 | 162 m2 | $138.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R89 | Site 6 | 8 | Install 3.0m Wide Precast Median - 2 Cap Units, 4 Middle Units (Supplied by TOC) | 1 EA | 1 EA | $139.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R90 | Site 6 | 9 | Concrete Pedestrian Ramp c/w Tactile Plates | 2 EA | 2 EA | $140.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R91 | Site 6 | 10 | Pedestrian Crossing | 15 l.m | 15 l.m | $141.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R92 | Site 6 | 11 | Pedestrian Crossing Signs c/w Base | 4 EA | 4 EA | $142.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R93 | Site 6 | 12 | Relocate Existing Signage | 1 EA | 1 EA | $143.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R94 | Site 6 | 13 | Supply and Install Signage | 1 EA | 1 EA | $144.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R100 | Site 7 | 1 | General Requirements | 1 LS | 1 LS | $150.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R101 | Site 7 | 2 | Traffic Control and Accomodation | 1 LS | 1 LS | $151.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R102 | Site 7 | 3 | Erosion and Sediment Control | 1 LS | 1 LS | $152.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R103 | Site 7 | 4 | Concrete Sidewalk Removal | 10 m2 | 10 m2 | $153.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R104 | Site 7 | 5 | Curb & Gutter Removal | 15 l.m | 15 l.m | $154.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R105 | Site 7 | 6 | Topsoil Stripping | 18 m2 | 18 m2 | $155.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R106 | Site 7 | 7 | Concrete Sidewalk Installation | 57 m2 | 57 m2 | $156.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R107 | Site 7 | 8 | Concrete Curb and Gutter | 10 l.m | 10 l.m | $157.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R108 | Site 7 | 9 | Concrete Pedestrian Ramp c/w Tactile Plates | 2 EA | 2 EA | $158.00 | EXACT_SAFE | Matched cleanly. |
| 2026-06-19!R109 | Site 7 | 10 | Pedestrian Crossings | 5.25 l.m | 5.25 l.m | $120.00 | STRUCK_THROUGH_DELETED | Owner struck through this row; excluded from active bidding. |
| 2026-06-19!R110 | Site 7 | 10 | Pedestrian Crossing Signs c/w Base | 2 EA | 2 EA | $650.00 | ITEM_COLLISION_PRICE_SWAP | Renumbered #11 -> #10; rate appears swapped. |
| 2026-06-19!R111 | Site 7 | 11 | Relocate Existing Signage | 2 EA | 2 EA | $1,500.00 | ITEM_COLLISION_PRICE_SWAP | Renumbered #12 -> #11; rate appears swapped. |
| PDF File | Page | Add.# | Level | Extracted Requirement & Exact Source Quote |
|---|---|---|---|---|
| owner_02_addendum_01.pdf | p.1 | 1 | WARNING | Required deliverable / compliance item: Safety Plan D Item No. Questions 1. Question: Per RFQ section 4.2.1.5 is a Project Specific Safety Plan an acceptable alternative to COR certification requirements? |
| owner_02_addendum_01.pdf | p.1 | 1 | WARNING | Required deliverable / compliance item: COR/SECOR e Project Specific Safety Plan will be evaluated under Category 4 in lieu of COR/SECOR Certified. If successful, the proponent shall submit a Project Specific Saf |